NEW IPSWICH - A wind farm developer has taken its plans to install five wind turbines in New Ipswich and Temple directly to the state, bypassing the planning and zoning boards in both towns.
Timbertop Wind, a subsidiary of Pioneer Green Energy of Texas, has proposed a wind farm on contiguous land in Temple and New Ipswich. The $25 million project would include five, three-megawatt Siemens wind turbines - two in New Ipswich and three in Temple.
According to Tim Drew, administrator of the Department of Environmental Services Public Information and Permitting Unit, it's not unusual for a developer to take its case to the state, bypassing town land use boards. In some cases, it's mandatory. Any project over 30 megawatts fall immediately under the jurisdiction of the Site Evaluation Committee (SEC), he said. The Temple/New Ipswich project is only 15 megawatts, so Timbertop Wind had to petition the Site Evaluation Community to take jurisdiction.
According to documents filed with the DES by attorney Thomas B. Getz of Devine Millimet, the request arises from town ordinances requiring setbacks, lighting requirements and noise limitations.
Those ordinances, according to Getz, "impose substantive requirements inconsistent with SEC precedent and state law."
Getz also argued that because the two towns have different ordinances, the case becomes a regional one, and should fall in the domain of the state.
But Ed Dekker, member of the New Ipswich Planning Board, said Timbertop's move to bypass the towns is intended to thwart the will of the people who voted overwhelmingly to pass tight restrictions on wind farms in their communities.
"The will of the people of New Ipswich was made clear by their votes, and it's inappropriate for the state to override the people of New Ipswich," Dekker said.
Drew said if the state does agree to take the case, the process will begin with public hearings, and will include hearings in which both sides will be required to present evidence. The Attorney General's Office represents local communities in the proceedings.
Ed Cherian of Iberdola Energy, the group responsible for both the Lempster wind farm project that went online four years ago and the Groton wind farm - which just started feeding power into the grid Friday - said the state process is arduous.
"Having gone through the process twice, I can say that it's extremely comprehensive and they leave no stone unturned," said Cherian.
In Lempster, the 24-megawatt project started with the local land use boards but became so overwhelming to both the planners and the town, that both parties petitioned the state to step in, Cherian said. And in Grafton, the size of the farm - 48 megawatts - placed it immediately in the state's purview.
"It's a very long, very costly process, almost like going to trial," said Cherian. "And anyone who's interested can have a seat at the table."
Drew said if the state agrees to take jurisdiction, public hearings could begin as soon as February or March.
Nancy Bean Foster may be reached at nfoster@newstote.com.
Timbertop Wind, a subsidiary of Pioneer Green Energy of Texas, has proposed a wind farm on contiguous land in Temple and New Ipswich. The $25 million project would include five, three-megawatt Siemens wind turbines - two in New Ipswich and three in Temple.
According to Tim Drew, administrator of the Department of Environmental Services Public Information and Permitting Unit, it's not unusual for a developer to take its case to the state, bypassing town land use boards. In some cases, it's mandatory. Any project over 30 megawatts fall immediately under the jurisdiction of the Site Evaluation Committee (SEC), he said. The Temple/New Ipswich project is only 15 megawatts, so Timbertop Wind had to petition the Site Evaluation Community to take jurisdiction.
According to documents filed with the DES by attorney Thomas B. Getz of Devine Millimet, the request arises from town ordinances requiring setbacks, lighting requirements and noise limitations.
Those ordinances, according to Getz, "impose substantive requirements inconsistent with SEC precedent and state law."
Getz also argued that because the two towns have different ordinances, the case becomes a regional one, and should fall in the domain of the state.
But Ed Dekker, member of the New Ipswich Planning Board, said Timbertop's move to bypass the towns is intended to thwart the will of the people who voted overwhelmingly to pass tight restrictions on wind farms in their communities.
"The will of the people of New Ipswich was made clear by their votes, and it's inappropriate for the state to override the people of New Ipswich," Dekker said.
Drew said if the state does agree to take the case, the process will begin with public hearings, and will include hearings in which both sides will be required to present evidence. The Attorney General's Office represents local communities in the proceedings.
Ed Cherian of Iberdola Energy, the group responsible for both the Lempster wind farm project that went online four years ago and the Groton wind farm - which just started feeding power into the grid Friday - said the state process is arduous.
"Having gone through the process twice, I can say that it's extremely comprehensive and they leave no stone unturned," said Cherian.
In Lempster, the 24-megawatt project started with the local land use boards but became so overwhelming to both the planners and the town, that both parties petitioned the state to step in, Cherian said. And in Grafton, the size of the farm - 48 megawatts - placed it immediately in the state's purview.
"It's a very long, very costly process, almost like going to trial," said Cherian. "And anyone who's interested can have a seat at the table."
Drew said if the state agrees to take jurisdiction, public hearings could begin as soon as February or March.
- - - - - - - -
Nancy Bean Foster may be reached at nfoster@newstote.com.
Monadnock Region » Events
- Pelham High nurse named School Nurse of the Year - 0
- MAKE SURE IT'S ME Opens at West End Studio Theatre - 0
- Harmonica Master James Cotton forced to postpone May 25 Londonderry Performance - 0
- Group continues effort to expand Cotton Valley Trail in Broofield - 0
- For Bedford girl, exploring the world in geography bee a ‘great thing to do’ - 0
- Loon Mountain Resort Unleashes New Obstacles for July 13 Monster Mud Run - 0
- Location Change for N.H. Fish and Game Commission Meeting June 12 - 0
- Jim Beauregard's Tasting Notes: Samuel Adams makes its can debut - 0
- Parents can plan ahead, model healthful habits... and not stress out - 0
Reviving the Piscataqua River Wherry
READER COMMENTS: 0Press Releases
Help Combat Invasive Plants; Loaner Tools & Statewide Web Resource
READER COMMENTS: 0GREENLAND, N.H. -- Groups working to combat invasive plants on the Seacoast can now borrow some tough "Weed Wrenching" tools to make their efforts more effective.
Cranmore Opens for Spring/Summer Operations on May 25
READER COMMENTS: 0NORTH CONWAY, NH – Cranmore Mountain opens for its third summer season on Saturday, May 25, 2013. Cranmore's Mountain Adventure Park is sure to make a memorable Memorial Day weekend for...
0
29th Annual Chowder Fest Kicks-Off Summer on June 1st
0
Loon Mountain Resort Opens for Summer May 25
0
Seven Earn N.H. Fish and Game Commission Awards of Excellence